Glimpses of the Mountain Tunnel for the Mumbai-Ahmedabad High-Speed Rail Corridor project.
Officials clarified that only a temporary access structure for the Mumbai-Ahmedabad bullet train project's Ulhas river bridge was affected by heavy rains in Thane, not the permanent bridge itself. The National High Speed Rail Corporation Limited (NHSRCL) confirmed the incident did not impact the project's design, safety, or execution.
The Mumbai-Ahmedabad bullet train project has achieved a significant milestone with the excavation of a mountain tunnel in Palghar, Maharashtra, marking the third such achievement in the district within the last five months. This progress underscores the rapid construction pace in a geographically challenging section of the high-speed rail corridor.
Railway Minister Ashwini Vaishnaw will inaugurate the underground tunnel-boring work from Vikhroli to the Bandra Kurla Complex station in Mumbai on Sunday, marking the maiden use of a tunnel boring machine for the country's first bullet train project, between Mumbai and Ahmedabad.
India's move to opt for Japanese bullet trains on the Mumbai-Ahmedabad route had raised concerns in China which is competing with Japan to build high-speed rail networks in India.
A 4.88 km tunnel between Shilphata and Ghansoli for the Mumbai-Ahmedabad bullet train project achieved a breakthrough, marking a significant milestone in the project's construction.
The Bullet Train project between Mumbai and Ahmedabad has achieved significant progress with the completion of 386 km of pier foundation and 272 km of viaduct. Track laying is expected to begin soon as all other infrastructure work is ready.
The transportation infrastructure business of L&T Construction has secured mega contract from the National High-Speed Rail Corporation Ltd (NHSRCL) to construct 87.569 km of the bullet train project.
One worker was killed and six others injured after a girder launcher fell on them during the construction of a high-speed rail corridor for the upcoming bullet train project near Karjan town in Gujarat's Vadodara district on Thursday, officials said.
A segmental launching gantry used for construction at a bullet train project site near Ahmedabad accidentally skid from its position and affected the adjoining railway line, disrupting the movement of several trains, officials said on Monday.
The incident took place at Vasad village located on the under-construction Bullet Train route, said district superintendent of police Gaurav Jasani.
L&T on Thursday said its construction arm has won a large contract for the bullet train project. L&T Construction has bagged the project from National High-Speed Rail Corporation Ltd (NHSRCL). "The railways business of L&T Construction has secured acontract from NHSRCL to construct 116 route km of High-Speed ballastless track works for Mumbai-Ahmedabad High-Speed Rail (MAHSR) project, popularly referred to as the bullet train project," the company said in a statement.
'Once finished, the project will reduce the travel time between Mumbai and Ahmedabad to just over two hours.'
The Bombay high court on Thursday said the Mumbai-Ahmedabad bullet train project is of 'national importance and in public interest', and dismissed a petition filed by Godrej & Boyce company challenging the acquisition proceedings initiated by the Maharashtra government and the NHSRCL in suburban Vikhroli for the project.
With land acquisition completed and infrastructure work streamlined, India's bullet train dreams are slowly, but finally, inching closer to reality.
As per the said order, a 50 m buffer zone must be created around the area that hosts the mangroves and no construction activity or dumping of debris can be permitted within this buffer zone.
L&T, Ircon International and Tata Projects have showed interest in a tender issued by the National High Speed Rail Corporation, implementing agency for the project. The tender is for construction of stations, bridges, viaducts, maintenance depots and tunnels.
The first consortium includes Afcons Infrastructure, IRCON International and JMC Projects, while the second group of companies include NCC, Tata Projects and J. Kumar Infra Projects.
Railway Minister Suresh Prabhu is targeting the commissioning of the project by 2023-24
In a significant development, Indian Railways on Thursday joined hands with China to increase speed in its existing rail network, modernise stations and enhance mutual cooperation in the sector in the country.
Amid protest over the proposed ambitious semi-highspeed SilverLine rail project, also known as K-Rail, the Kerala government on Saturday published the detailed project report that estimated the cost of project to be Rs 63,941 crore.
The National High Speed Rail Corporation Limited has invited bids for the design and construction of an underground station at Mumbai's Bandra Kurla Complex and for a tunnel for the bullet train project, Railway Minister Ashwini Vaishnaw said on Friday. This is the first set of bids invited after the rebel Shiv Sena leader Eknath Shinde-led government came to power in Maharashtra. The new government has given the green light to the project, which remained dormant during the erstwhile Uddhav Thackeray-led dispensation.
The Union Budget for 2026-27, presented by Finance Minister (FM) Nirmala Sitharaman on Sunday, which was a first, had an excellent domestic macro backdrop. According to the first advance estimates, gross domestic product (GDP) in constant prices is projected to grow 7.4 per cent in the current financial year, against 6.5 per cent in 2024-25.
The state government and the company are embroiled in a legal dispute since 2019 over the acquisition of the company-owned land in Vikhroli for the bullet train project.
The bullet train is expected to cover 508 km between Mumbai and Ahmedabad in about two hours.
Of the Rs 1.10 lakh crore investment required for the project, Japan is providing Rs 88,000 crore as a soft loan at 0.01 per cent interest.
Apart from land acquisition, another major cause for concern before the project is cost escalation owing to a fall in the rupee against the Japanese yen.
The court directed the NHSRCL to file a correction statement within a month to the effect that the TDS deducted by it while paying the compensation amount to Patil was not liable to be deducted.
The high-speed train line in a region already well-connected by rail, road and airways may have to struggle to stay viable
From highways connecting once-remote regions to aviation networks carrying millions, India's infrastructure story is one of transformation.
Modi showed the green flag to the train connecting Sahibabad and Duhai Depot stations, marking launch of the RRTS in India. The train can run at a speed of 180 km per hour,
Trains of the Regional Rapid Transit System (RRTS), to be inaugurated by Prime Minister Narendra Modi on Friday, will be known as 'Namo Bharat', Union Minister Hardeep Singh Puri announced on Thursday.
The project, the foundation stone for which was laid by Prime Minister Narendra Modi and his Japanese counterpart Shinzo Abe in September 2017, is facing resistance in eight districts of Gujarat, through which the train will run.
DMRC-like SPV to be floated in a month for the Rs 98,000 crore Mumbai-Ahmedabad corridor.
The change in leadership at the railway ministry comes at a time when the national transporter is grappling with low passenger earnings even as it is trying to increase freight loading and open up its doors to private investment. Union Minister Ashwini Vaishnaw took charge from Piyush Goyal who got the railway portfolio in 2017 after Prime Minister Narendra Modii dropped Suresh Prabhu from the Union Cabinet. Completing freight corridors, negotiating land for the bullet train, and speeding up monetisation plans would be some of the major focus areas for Vaishnaw.
While farmers in Gujarat are rejecting the compensation package, farmers in Maharashtra say they do not wish to part with their land for a project that largely benefits Gujarat.
'Modi and Abe are working seriously for India-Japan bonhomie to grow stronger.' 'It is a win-win situation for both countries and the future look promising,' says Rajaram Panda, the Indian Council for Cultural Relations India Chair Visiting Professor at Reitaku University, Japan.
Prime Minister Narendra Modi on Friday flagged off the Gandhinagar-Mumbai Vande Bharat Express semi-high speed train.
Semi-high-speed 'Namo Bharat' train services on the 17-km priority section of India's first Regional Rapid Transit System (RRTS) rail corridor will be opened for people from Saturday morning.